Walk me through how you build a project schedule from a fresh scope of work. What do you produce, and in what order?
FoundationalHow to answer
What they’re really asking
They want to see whether you understand the mechanics of schedule development rather than just owning a Gantt chart someone else built. The signal is structured, bottom-up thinking.
Strong answer structure
Start from the scope/WBS to decompose deliverables into work packages. Define activities, sequence them with logical dependencies (FS/SS/FF/SF), estimate durations (resource-based, not just calendar), assign resources, then let the network calculate the critical path. Add calendars, constraints, and milestones. Baseline only after a logic and resource-loading review. Mention you avoid hard date constraints and prefer logic-driven dates.
Likely follow-ups
- How do you decide the right level of WBS granularity?
- What's the difference between a schedule constraint and a dependency, and why does it matter for float?